    How to track DISCOM approvals and net metering across projects

    Installation takes days. Feasibility, inspection and the net meter take weeks, and each DISCOM behaves differently. A tracker design that shows which project is waiting on whom, for how long.

    GC
    GarunaCDX Editorial
    Editorial team
    Oct 19, 2026 4 min read
    Key takeaways
    • Approvals are the longest unmanaged queue in a rooftop business. Make the queue visible.
    • One workflow per DISCOM. Documents, portals and delays differ by state.
    • Record who each project is waiting on, not just a status word like pending.
    • Do not install before feasibility is approved; one practitioner source warns DISCOMs may refuse net metering if you do (reported).
    • Practitioner-reported ranges are a starting guess. Your own history per DISCOM is the real benchmark.

    Quick answer

    Track every rooftop project through a fixed set of external steps: application, feasibility, sanction, installation, inspection, meter installation and commissioning. For each step record the date started, the date done and who it is waiting on, and keep a separate workflow per DISCOM because documents and delays differ. The number to put on your wall is days waiting per project. Practitioners report feasibility in days to about two weeks and net metering in one to four weeks, but timelines vary by DISCOM, so measure your own.

    Why do approvals need their own tracker?

    Because installation is the short part. A crew can finish a residential system in a day or two. The project then waits on parties you do not control: the DISCOM for feasibility, the inspector, the meter installer, and for scheme projects the national portal. While it waits, nothing looks wrong on site and money stays unbilled. See why this drives cash.

    What are the stages?

    External steps on a typical rooftop project (our model; names differ by DISCOM)

    1. Step 1

      Application and consumer details

      Consumer number, sanctioned load, category and owner or society consent for the roof.

    2. Step 2

      Feasibility

      DISCOM checks transformer and service line capacity. Do not install before this is approved.

    3. Step 3

      Design, order and installation

      BOM uses compliant equipment; serial numbers and photos are recorded on site.

    4. Step 4

      Commissioning upload

      Completion report, photos and component details submitted.

    5. Step 5

      Inspection

      DISCOM inspects. Backlogs here are a known delay.

    6. Step 6

      Net meter installed

      Bidirectional meter fitted; project can export.

    7. Step 7

      Subsidy claim and final billing

      Where applicable. See the subsidy tracking article.

    How long does each step take?

    It depends on the DISCOM, and published service levels are patchy. One practitioner guide aimed at EPCs reports, from the author’s experience rather than any official standard: feasibility in a few days to about two weeks; inspection and net metering roughly one to four weeks after installation; and two to four months end to end for scheme projects including subsidy. Treat these as a starting guess.

    The better benchmark is your own history. Once you record dates for every project, you can see that DISCOM A averages nine days to feasibility and DISCOM B averages twenty. That tells you how to schedule crews and what to promise customers.

    What should the tracker record?

    FieldWhy it matters
    DISCOM and stateSelects the workflow and document list
    Consumer number and sanctioned loadMany states cap net-metered capacity at sanctioned load, so confirm before sizing
    Date applied, date feasibility approvedStarts and stops the first clock
    Date installedStarts the inspection clock
    Inspection date, meter installed dateMarks export-ready
    Documents submitted, documents rejectedRejections are the hidden delay
    Waiting onA person or body, not the word pending
    Next action and ownerWithout an owner, a queue is just a list
    Days waitingThe headline number

    What should the view look like?

    One screen, sorted by days waiting, grouped by DISCOM. At the top: projects that have waited longest. A project that has been with the DISCOM for more than your usual turnaround is a call to make today. A manager should be able to read it in two minutes without opening a project.

    What goes wrong most often?

    • Out-of-order installation. A source warns DISCOMs may refuse net metering if work starts before feasibility. Add a hard stop to scheduling.
    • Mismatched data. Consumer number, serial numbers and bank details differing between forms cause rejections. Enter each once.
    • Nobody owns the chase. Name a person per DISCOM.
    • No evidence trail. Keep dated copies of every submission so disputes are quick.

    Where does this not apply?

    Large utility-scale projects have their own regulatory and transmission process, with far longer timelines (see the market piece). This page is about rooftop and small C&I net-metered projects.

    What to do this week

    1. List every project currently waiting on an external body, with the date it started waiting.
    2. Calculate your real turnaround per DISCOM from the last ten projects.
    3. Assign one owner per DISCOM for follow-up.

    Part of the guide Running a solar EPC business on connected systems.

    Approvals check
    Send us your last ten approvals with dates. We will show your real turnaround per DISCOM.
    Talk to us

    The stage list and tracker fields are our own model. Timelines and the out-of-sequence warning come from one vendor practitioner guide to PM Surya Ghar for EPCs (SurgePV), which says its figures are the author’s experience and discloses a commercial relationship with an installer. They are not official service levels. Check your DISCOM’s rules and the national portal.

    Your verdict
    Was this article useful?
    GC
    Written by
    GarunaCDX Editorial
    Editorial team

    Engineers, product and growth folks at GarunaCDX writing about the systems we build for clients.

    View all articles
    Share
    Planning something similar?

    Let's talk about your build.

    Tell us what you are building. A founding engineer replies within one working day with how we would approach it.

    FAQ

    Frequently asked questions

    It varies by DISCOM and state. One practitioner guide reports roughly one to four weeks after installation for inspection and meter installation, and feasibility in a few days to about two weeks. These are experience-based figures, not official service levels, so check your state rules and your own history.

    Application date, DISCOM, consumer number, sanctioned load, feasibility status and date, inspection date, meter installation date, commissioning date, documents submitted and who the project is waiting on.

    Because document lists, portals, inspection practices and typical delays differ. A single generic approval status hides where the delay actually is.

    A practitioner source warns that installing out of sequence can lead DISCOMs to refuse net metering. Confirm the rule for your DISCOM before scheduling a crew.

    The GarunaCDX build log

    Industry insights, once a month

    New case studies, healthcare, marketplace, B2B SaaS and industrial breakdowns, and the engineering notes behind what we ship. One short email a month, no fluff.

    We never share your data — see our Privacy Policy for details.