    The solar project lifecycle: stages, owners, documents and handoffs

    Lead to O&M in nine stages: who owns each, which documents move, and which handoffs break.

    GC
    GarunaCDX Editorial
    Editorial team
    Oct 19, 2026 2 min read
    Key takeaways
    • Nine stages, each with one owner and a clear output.
    • Most breaks happen at handoffs, not inside stages.
    • Document sets differ by state and DISCOM; confirm yours.
    • Draw your own lifecycle before choosing any tool.

    Quick answer

    A rooftop or C&I solar project passes through nine stages: lead, survey, design and quote, contract, procurement, installation, approvals and commissioning, billing and collection, and O&M. Each stage has an owner, a document set and a handoff. Most failures happen at handoffs: survey to design, design to procurement, site to accounts. Map your own lifecycle on one page before you choose a system.

    The nine stages

    Lead to O&M (our model; adapt to your business)

    1. 1

      Lead

      Owner: sales. Output: qualified enquiry with consumer details.

    2. 2

      Survey

      Owner: surveyor. Output: structured site data and photos.

    3. 3

      Design and quote

      Owner: design. Output: system size, BOM, price. The quote BOM becomes the project budget.

    4. 4

      Contract

      Owner: sales and finance. Output: signed terms, milestone schedule, guarantees if any.

    5. 5

      Procurement

      Owner: purchase. Output: POs linked to BOM, delivery dates, serials at receipt.

    6. 6

      Installation

      Owner: site lead. Output: checklist, photos, serials, change log.

    7. 7

      Approvals and commissioning

      Owner: approvals desk. Output: DISCOM steps, meter, commissioning report, subsidy claim where applicable.

    8. 8

      Billing and collection

      Owner: accounts. Output: milestone invoices, collections, retention release.

    9. 9

      O&M

      Owner: service lead. Output: AMC, tickets, renewals, warranty claims.

    Typical documents by stage

    Document sets differ by state, DISCOM and project type. Confirm yours; treat this as a prompt, not a legal list.

    StageTypical documents
    SurveySurvey form, roof photos, load and meter details, owner or society consent
    QuoteDesign sheet, BOM, price, validity
    ContractAgreement, milestone schedule, guarantee terms
    ProcurementPurchase orders, delivery challans, supplier invoices, warranty documents
    InstallationInstallation checklist, serial list, photo set, change log
    ApprovalsApplication, feasibility, inspection, meter documents, commissioning report
    BillingMilestone evidence, tax invoices, collection receipts
    O&MAMC agreement, visit reports, warranty claim packs

    Where do handoffs break?

    The four handoffs that break most often

    structured dataBOM linesserials and photosevidence for billingSurveyInstallationDesignApprovalsProcurementAccounts
    Our model. Each handoff is a place where data should be reused, not retyped.

    How to use this chapter

    Draw your own lifecycle on one page: stages, owner, output, and the waiting time between. Where two managers draw it differently, resolve it first. A new system will expose the disagreement. Then take the requirements list in what a solar ERP must do.

    Next: costing and margin control. Back to start here.

    The stages, owners and document prompts are our own model and are not a statutory checklist. Confirm requirements with your DISCOM and professional advisers.

    Your verdict
    Was this article useful?
    GC
    Written by
    GarunaCDX Editorial
    Editorial team

    Engineers, product and growth folks at GarunaCDX writing about the systems we build for clients.

    View all articles
    Share
    All guides

    Keep going with the next handbook.

    Chapter-by-chapter guides from the engineers who build these systems for clients.

    Browse guides
    FAQ

    Frequently asked questions

    In our model: lead, survey, design and quote, contract, procurement, installation, approvals and commissioning, billing and collection, and O&M.

    Survey to design, design to procurement, installation to approvals, and site to accounts. Each depends on information typed once and reused.

    The GarunaCDX build log

    Industry insights, once a month

    New case studies, healthcare, marketplace, B2B SaaS and industrial breakdowns, and the engineering notes behind what we ship. One short email a month, no fluff.

    We never share your data — see our Privacy Policy for details.